2012 TAS Compliance Criteria

2012 TAS Compliance Criteria

Building Permit Required by State, County, or Local GovernmentBuilding Permit NOT Required by State, County, or Local Government
*Certified to be Complete: If the government entity does not certify permit or permit extensions to be complete, the compliance date would be determined by the date the last application for a building permit or permit extension is received by a state, county, or local government.

**1994 TAS or 2012 TAS: It is not acceptable to apply both standards to one EABPRJ project number -
full compliance with either the 1994 TAS or 2012 TAS is required.
Permit or Permit Extension Certified to be Complete:*Applicable TAS Standard:Start of Physical Construction or Alteration:Applicable TAS Standard:
Between April 1, 1994 and March 14, 20121994 TAS or 2012 TAS**Between April 1, 1994 and March 14, 20121994 TAS or 2012 TAS**
On or after March 15, 20122012 TASOn or after March 15, 20122012 TAS